Friends of The Helicopter Museum

Whirlwind XD163 Restoration - The Seventh 8 Months

Repainting of Tail Skid Components Fitting the Tail Skid Assembly
After overhauling and replacing the skid components, Mike Addicott refitted them on 7th July 2007.
XD163 Cabin Door Steps Forward Wheel and Oleo after Refurbishment
On 8th August 2007 Stuart refitted the cabin step, after refurbishment and repainting. The two forward oleos and castoring wheels were rebuilt before installation in mid-August 2007. 
Re-painting of Main Rotor Blades Started Re-fitting of Second Main Rotor Blade
On 16th August 2007 work started on the refurbishing and painting of XD163's three main rotor blades. This work was finished by late October 2007 and the first blade was refitted to the rotor head. On 3rd November 2007 the remaining two blades were fitted and installed in their folded position.
Cabin Floor Panels were Cleaned up and Painted Cabin Floor after the Panels had been Layed
By mid-December 2007, work on the refurbishment of the under-floor fuel tanks was nearing completion and the flooring panels were being cleaned, repaired and re-painted (above left). Re-laying of the floor panels was completed on 29th December, with some paint retouching finished on 5th January 2008.
Spigot on End of Grey Radius Strut had Moved out of its Bracket bearing Fractured Outboard Bearing was Replaced
It had been hoped that XD163 could be rolled out into the Display Hangar on 13th January 2008 but it was found that the left side main undercarriage leg, which acts as a radius strut for the assembly, had not been properly secured into its underfloor, inboard, bracket bearing (above left). The consequential extra load on the outboard bearing had caused it to fracture (above right).
The Left Side Strut was Re-fitted into its Bearing Strut and Spigot were Pushed Fully Home
A replacement outboard bearing bracket was obtained from a donor Whirlwind and fitted to XD163. On 9th February 2008 the left main undercarriage leg and strut were refitted (above left) with close monitoring to ensure that the spigot, on the end of the strut, was pushed home before being rotated and fully locked into its inboard bearing bracket (above right). The integrity of the right side fittings was also carefully checked and found to be satisfactory, before the flooring was replaced.
Restoration Volunteers push XD163 into its Display Position Tail Rotor Assembly was fitted by Mike and Stuart
By 15th February 2008 the Whirlwind restoration was 99% complete so the machine was rolled out into the Display Hangar to facilitate other aircraft movements, which were delayed four weeks previously because of XD163's problems. With XD163 in its display position the tail rotor assembly was installed and the nose cone was re-fitted. A few interior details still needed some further work but most of these were attended to after the helicopter went on public display.
XD163 back on Display
Back to Page 6 Restoration Index